GS Group held a groundbreaking ceremony for the Donghae GS AI Data Center on the 28th. The project is planned for Donghae, Gangwon Special Self-Governing Province, and is being developed at Asia’s largest scale, according to Yonhap.
Key takeaways · 4
- 01
GS says the project will have two 1.2-gigawatt phases, totaling 2.4 gigawatts.
- 02
GS targets the first 100-megawatt center for completion in the second quarter of 2028.
- 03
The company targets bringing the center online in 2029.
- 04
A September investment plan put 15 trillion won toward the first phase; another report gives a figure of up to 120 trillion won, without explaining how the figures relate.
A phased build in Donghae
The project is being built at the Bukpyeong Second General Industrial Complex in Donghae.[1] GS plans two phases of 1.2 gigawatts each, for total project capacity of 2.4 gigawatts.[1] GS targets bringing the center online in 2029, while planning to complete its first 100-megawatt center in the second quarter of 2028.[1] Those milestones distinguish an initial facility target from the longer project timeline; the reports do not say that the full 2.4 gigawatts will be available by 2028.[1]
Site plans and investment figures
GS plans to divide a roughly 80,000-pyeong site into three zones for centers with combined capacity of 700 megawatts.[1] It also plans a 500-megawatt center on an additional site.[1] The investment figures require care: GS announced a 15 trillion won investment plan for the first phase in September, while another report gives a figure of up to 120 trillion won.[1][3] The cited evidence does not explain how those amounts relate, so they should not be treated as interchangeable estimates of the same phase.[1][3]
Power and construction are central
AI data centers use high-performance servers for the large-scale computing needed for AI training and inference.[3] Stable electricity supply and cooling systems are critical to their operation.[3] GS says it brought together the group’s energy experience and GS Engineering & Construction’s design and construction capabilities.[1] It selected the Donghae site after assessing its size, power-supply conditions and transport access.[1] GS also says its existing energy operations across South Korea offer links to the large-scale power supply data centers require.[1]
Local support and stated aims
GS signed a cooperation agreement with Gangwon Province and Donghae in July and completed permitting procedures, including a power-grid impact assessment and building permit.[1] The company said the investment would create local jobs and opportunities for local businesses.[1] President Lee Jae-myung attended the ceremony and thanked GS for its investment; he said the government would support AI data centers as drivers of local economic growth.[1] About 270 people, including local residents, attended.[2] GS says it plans to use Donghae as a base for expansion into other regions.[1]
For professionals assessing AI infrastructure, the announcement offers concrete scale and timing targets, while also highlighting that the full build is phased. The project’s reliance on electricity supply, cooling and permitting makes those considerations relevant to planning, not just compute capacity.
Why it matters
AI training for your team
kju.ai is built for teams: daily sessions, team analytics, and rollout support for your organization.
How this developed
28 November 2026
GS begins work on planned 2.4-GW Donghae AI data center