Drax, Brookfield and Radiant plan AI data center in Yorkshire
Drax said it signed an agreement with Brookfield and Radiant to jointly develop an AI data center at the Drax Power Station estate in North Yorkshire. Brookfield estimates total investment, including semiconductors, could exceed £20 billion ($26.8 billion).

Key takeaways · 4
- 01
Drax, Brookfield and Radiant signed an agreement to jointly develop the project at Drax’s North Yorkshire power station estate.
- 02
Brookfield estimates the first phase needs £2.5 billion in initial investment; total project investment, including semiconductors, could exceed £20 billion ($26.8 billion).
- 03
The first phase targets up to 100 megawatts and operation in the first quarter of 2028.
- 04
The first phase is planned to use grid power and depends on approvals and securing a tenant; final investment decisions have not been made.
A large-scale UK data center plan
Drax said it had signed an agreement with Brookfield and Radiant to jointly develop an AI data center at the Drax Power Station estate in North Yorkshire.[1] The project is planned for the north of England.[1] Brookfield estimates total investment could exceed £20 billion ($26.8 billion), including spending on semiconductors, and puts the initial investment for the first phase at £2.5 billion.[1] These are estimates and a development agreement, not a final investment commitment.[1]
Capacity and timing targets
The first phase is intended to provide up to 100 megawatts of capacity and is targeted to become operational in the first quarter of 2028.[1] Drax said it is aimed at commercial customers from early 2028.[1] A further 500 megawatts is planned to come online between 2028 and 2031.[1] The broader ambition is to secure more than 1 gigawatt of capacity at the site, but no date has been specified for reaching that target.[1] The phases and target dates are plans, rather than confirmed delivery milestones.[1]
Approvals and power are key conditions
The first phase is planned to use power from the grid.[1] Drax said it depends on planning, regulatory and network approvals, as well as securing a tenant.[1] Drax also said final investment decisions had not yet been made.[1] For teams assessing the proposal, those conditions are central: the stated capacity and schedule do not by themselves confirm that the project will proceed on the proposed timetable.[1] The first phase’s commercial-customer target is early 2028.[1]
A response to Europe’s infrastructure challenge
CNBC placed the proposal in the context of Europe’s effort to build AI infrastructure amid high energy and land costs, and reported that the U.S. had moved ahead of Europe in developing large AI data centers.[1] It also reported that the U.K. has faced high energy costs and long waits for businesses seeking grid connections.[1] Microsoft had pulled out of a deal to anchor an Nscale data center near London amid power-grid connection delays, CNBC reported.[1] The Nordics benefit from abundant power and available land, while Finland has seen major data-center commitments; Google said in September it would invest at least 13 billion euros in AI infrastructure there.[1]
The proposal puts a sizeable AI infrastructure plan on the table, but its scale and schedule are still conditional. Professionals evaluating data-center demand, power access or project investment should distinguish the stated targets from secured approvals, a tenant and a final investment decision.
Why it matters
Bring this to your team — one session a day, built for your industry.
kju.ai is built for teams: daily sessions, team analytics, and rollout support for your organization.
For teamsHow this developed
3 November 2026
Drax, Brookfield and Radiant plan AI data center in Yorkshire